Peters construction installing loam in ditchline and rip rapping culvert ends. One driveway culvert extended with 2 ft. of 12 in. dia. aluminum culvert ea end. Jeff Nest on site to clean out existing driveway culverts that were not replaced as part of this project.
Monday, October 18, 2010
Thursday, October 14, 2010
Sidewalk Work 10-14-10
Peters Construction continued ditching work on east side of road. Jeff Nest, working for town, started clean out of driveway culverts that were not replaced. Discussed erosion and sedimentation control measures for expected 1 -3 inch rainstorm on Friday. Peters said they had been in contact with KKWWD and will relocate fire hydrant per their request.
Wednesday, October 13, 2010
Sidewalk Work 10-13-10
Peters Construction ditching on east side of Cat Mousam Road. Discussed cleaning out existing driveway culverts to remain and location of mailboxes. Brendan from Peters spoke with Dayton Sand and Gravel and the sidewalk paving work has been postponed until Saturday at the earliest.
Tuesday, October 12, 2010
Sidewalk work 10-12-10
Peters Construction completed fine grade on entire sidewalk. Driveways adjusted and prepped for paving.
Friday, October 8, 2010
Sidewalk work 10-08-10
Dayton Sand and Gravel completed curb work to turnpike bridge. Dayton base paved sidewalk to adjust grade at first Coventry Woods entrance. Peters construction installing base gravel and fine grade gravel for sidewalk. Granite Curb adjusted to tie into new sidewalk at 2nd Coventry Woods entrance near the turnpike bridge.
Thursday, October 7, 2010
Sidewalk Work 10-07-10
Peters Construction on site with Chris Osterrieder of DeLuca Hoffman to go over sidewalk work between the Turnpike Bridge and Coventry Woods. Peters installing subgrade for new sidewalk. At areas where Cat Mosam Road was widened for the bridge, curb can be set on existing pavement.
Wednesday, October 6, 2010
Sidewalk Work 10-06-10
Peters Construction did some fine grade work in the morning, then stopped work for the day due to rain around 9:00 am.
Tuesday, October 5, 2010
Sidewalk Work 10-05-10
Peters construction fine grading sidewalk. Curb installed at transition area from Coventry Woods entrance near turnpike bridge. A short section of sidewalk paved with remainder of curb mix. Looked at 500 feet of paved swale area with Peters. Took elevation shots on existing white line at edge of road every 50 feet to determine grade change. Grade changes (in feet) every 50 feet were .7,.7,.7,.6,.4,.8,.8,.75,.75,.9. Discussed these elevation changes with Steve Blake of DeLuca Hoffman. All were over 1% except one so we decided to change paved swale to curb with tip downs at driveways. Peters to proceed on that basis.
Monday, October 4, 2010
Sidewalk Work 10-04-10
Peters Construction on Site with compacting sidewalk base gravel. Setting up elevations for fine grade. Discussed using stone dust for fine grade instead of Type A gravel in order to get a more consistent finish surface. Mike Claus and Steve Blake discussed by phone and gave Peters to ok to fine grade with stone dust.
Friday, October 1, 2010
Sidewalk Work 10-01-10
Thursday, September 30, 2010
Sidewalk Work 9-30-10
Dayton Sand and Gravel has based in sidewalk under curb and started paving cross cuts for new drainage. Swale area not opened up due to forecast rain event. Discussed relocation of mailboxes with Peters Construction. Noted 3 mailboxes on the sidewalk side of road which will have to be relocated to the backside of new curb. Discussed widening the sidewalk around the 3 mailboxes.
Wednesday, September 29, 2010
Sidewalk Work 9-29-10
Peters Construction has based in the sidewalk up to the portion of the paved swale. Some minor changes made to the curb layout at the Coventry Woods entrance. Peters reluctant to open up paved swale because of forecast heavy rain. Erosion control material being placed for possible rain event. Dayton Sand and Gravel may be in to do some paving work to prep the edge of roadside for curb installation.
Tuesday, September 28, 2010
Sidewalk Work 9-28-10
Peters Construction excavating to base depth for new sidewalk. Met with Steve Blake on site to go over existing pavement conditions. Light mist and 60 degrees for most of the day. Fairpoint on site to look at buried undergound phone line that has been abandoned. Line encountered by Peteres in excavation work.
Monday, September 27, 2010
Sidewalk Work 9-27-10
Friday, September 24, 2010
Sidewalk Work 9-24-10
5 cross culverts installed on Cat Mousam Road with basins on the sidewalk side. Gorham Sand and Gravel installing 2 Type F Basins in ditch line on opposite side of road from Sidewalk. Drainage pipe to ravine outlet installed. Gorham Sand and Gravel supervisor said remaining work would be completed by Peters Construction.
Thursday, September 23, 2010
Sidewalk Work 9-23-10
Gorham Sand and Gravel on Site for drainage work. Cross culvert installed at eastern Spiller Drive Entrance. 2nd cross culvert and structure installed across Cat Mousam Road. Start of 3rd cross culvert underway. Chris Osterrieder and I met with Gorham Sand and Gravel to discuss structure elevations, ditching, existing culverts and installation of an additional catch basin near the eastern Spiller Drive entrance.
Wednesday, September 22, 2010
Sidewalk Work 9-22-10
Peters Construction on site in morning. Cutting pavement with saw attachment for excavator. Drainage structures being delivered by Elm Street Vault.
In the afternoon Gorham Sand and Gravel delivered excavator and loader to install drainage structures and cross road pipes. Gorham Sand and Gravel personnel are accomplishing this work. One drainage structure and cross pipe installed. ADS pipe stockpiled roadside next to remaining drainage structure.