Peters construction fine grading sidewalk. Curb installed at transition area from Coventry Woods entrance near turnpike bridge.   A short section of sidewalk paved with remainder of curb mix.   Looked at 500 feet of paved swale area with Peters.  Took elevation shots on existing white line at edge of road every 50 feet to determine grade change.  Grade changes (in feet) every 50 feet were .7,.7,.7,.6,.4,.8,.8,.75,.75,.9.  Discussed these elevation changes with Steve Blake of DeLuca Hoffman.  All were over 1% except one so we decided to change paved swale to curb with tip downs at driveways.  Peters to proceed on that basis. 