Thursday, September 30, 2010
Sidewalk Work 9-30-10
Dayton Sand and Gravel has based in sidewalk under curb and started paving cross cuts for new drainage. Swale area not opened up due to forecast rain event. Discussed relocation of mailboxes with Peters Construction. Noted 3 mailboxes on the sidewalk side of road which will have to be relocated to the backside of new curb. Discussed widening the sidewalk around the 3 mailboxes.
Wednesday, September 29, 2010
Sidewalk Work 9-29-10
Peters Construction has based in the sidewalk up to the portion of the paved swale. Some minor changes made to the curb layout at the Coventry Woods entrance. Peters reluctant to open up paved swale because of forecast heavy rain. Erosion control material being placed for possible rain event. Dayton Sand and Gravel may be in to do some paving work to prep the edge of roadside for curb installation.
Tuesday, September 28, 2010
Sidewalk Work 9-28-10
Peters Construction excavating to base depth for new sidewalk. Met with Steve Blake on site to go over existing pavement conditions. Light mist and 60 degrees for most of the day. Fairpoint on site to look at buried undergound phone line that has been abandoned. Line encountered by Peteres in excavation work.
Monday, September 27, 2010
Sidewalk Work 9-27-10
Friday, September 24, 2010
Sidewalk Work 9-24-10
5 cross culverts installed on Cat Mousam Road with basins on the sidewalk side. Gorham Sand and Gravel installing 2 Type F Basins in ditch line on opposite side of road from Sidewalk. Drainage pipe to ravine outlet installed. Gorham Sand and Gravel supervisor said remaining work would be completed by Peters Construction.
Thursday, September 23, 2010
Sidewalk Work 9-23-10
Gorham Sand and Gravel on Site for drainage work. Cross culvert installed at eastern Spiller Drive Entrance. 2nd cross culvert and structure installed across Cat Mousam Road. Start of 3rd cross culvert underway. Chris Osterrieder and I met with Gorham Sand and Gravel to discuss structure elevations, ditching, existing culverts and installation of an additional catch basin near the eastern Spiller Drive entrance.
Wednesday, September 22, 2010
Sidewalk Work 9-22-10
Peters Construction on site in morning. Cutting pavement with saw attachment for excavator. Drainage structures being delivered by Elm Street Vault.
In the afternoon Gorham Sand and Gravel delivered excavator and loader to install drainage structures and cross road pipes. Gorham Sand and Gravel personnel are accomplishing this work. One drainage structure and cross pipe installed. ADS pipe stockpiled roadside next to remaining drainage structure.